Corridor Downtime Saved
⚑ ROI ACTIVE
38.4%
↑ +4.2hShadow Bundling
Track Availability Index
TARGET > 95%
96.2%
↑ +1.2%IRPWM Standard
Active Corridor Blocks
NOCTURNAL
02Active
01:30–04:45Possessory Windows
Pending Demands
02 P1 CRITICAL
06In Queue
↑ +2 NewCivil/OHE/S&T
White Corridor Gap
OPTIMAL LULL
3h 15m
01:30–04:45195m Window
Active Kavach TSRs
30 KM/H SPEED
01Enforced
↓ -1 ClearedSpeed Supervision

Section Interlocking & Track Circuit Schematic (CSMT - Kalyan 54 KM Quadrupled Corridor)

INTERLOCKING ROUTE:
AXLE COUNTER DUAL-DETECTION: HEALTHY (0 MISMATCH)
CLEAR
OCCUPIED
BLOCK SANCTIONED
FORM S&T/T-351 STATUTORY LOCKOUT: Automatic Train Stop Engaged β€” Signal Clamped Danger at S-12

Section locked for Joint Shadow Maintenance Block JB-2026-0926-01 (Dadar - Kurla UP Slow Line). Speed clamped to 30 km/h TSR.

ACT 14B ENFORCED
TC-01LINE CLEAR

CSMT - Byculla

UP_SLOWKM 0.0 - 4.8
S-02
25kV
105 km/h
TC-02OCCUPIED

Byculla - Dadar

DOWN_SLOWKM 4.8 - 9.2
S-06
25kV
110 km/h
TC-03BLOCK SANCTIONED

Dadar - Kurla

UP_SLOWKM 9.2 - 15.5
S&T LOCKOUT
S-12
25kV ISOLATED
30 km/h TSR
TC-04SLOTTED

Kurla - Ghatkopar

DOWN_FASTKM 15.5 - 21.8
S-18
25kV
80 km/h
TC-05LINE CLEAR

Ghatkopar - Thane

UP_FASTKM 21.8 - 34.0
S-24
25kV
120 km/h
TC-06OCCUPIED

Thane - Kalyan

5TH_LINEKM 34.0 - 54.0
S-32
25kV
130 km/h
TC-03

Dadar - Kurla (UP_SLOW)

Chainage: KM 9.2 to KM 15.5 β€’ Controlling Signal: S-12 β€’ Aspect: RED

Multi-Department Maintenance Demand Queue

6 Demands
πŸ”
Priority:
Joint Bundling Opportunity: 3 Requisitions share Track Circuit TC-03 (UP_SLOW). CP-SAT bundling prevents separate possessions and saves 195 min downtime.
TMS CivilP1 CRITICAL (94%)
TC-03UP_SLOWKM 14.2⏱️120m

USFD detected 35mm transverse rail fracture at Welded Joint W-42 (KM 14.220).

Section: Dadar - Kurla Up Slow Line
Ticket: CR-TMS-2026-8812β€’πŸšœCSM Continuous Tamping Machine #5109β€’+20m deadhead transit
TDMS OHEP1 CRITICAL (88%)⚑25kV OHE ISOLATION
TC-05UP_FASTKM 29.8⏱️110m

Damaged cantilever insulator bracket prone to flashover during high moisture morning hours.

Section: Ghatkopar - Thane Up Fast Line
Ticket: CR-TDMS-2026-5510β€’πŸšœOHE Wiring Train #12β€’+30m deadhead transit
TDMS OHEP2 SCHEDULED (72%)⚑25kV OHE ISOLATION
TC-03UP_SLOWKM 14.8⏱️90m

25kV AC Catenary dropper slack and contact wire wear exceeding 20% limit at Mast 14/18.

Section: Dadar - Kurla Up Slow Line
Ticket: CR-TDMS-2026-4309β€’πŸšœOHE Hydraulic Ladder Inspection Tower Wagon #60515β€’+15m deadhead transit
SMMS SignalP2 SCHEDULED (68%)
TC-03UP_SLOWKM 15.1⏱️60m

Audio Frequency Track Circuit (AFTC) tuning unit impedance drift and point machine detector calibration.

Section: Dadar - Kurla Up Slow Line
Ticket: CR-SMMS-2026-1192β€’πŸšœSignal Gang Maintenance Tool Vanβ€’+10m deadhead transit
TMS CivilP2 SCHEDULED (65%)
TC-04DOWN_FASTKM 21.4⏱️150m

Deep screening and ballast deficiency restoration around crossover point 104B.

Section: Kurla - Ghatkopar Down Fast Line
Ticket: CR-TMS-2026-9044β€’πŸšœBCM Ballast Cleaning Machine #302β€’+25m deadhead transit
SMMS SignalP3 ROUTINE (38%)
TC-02DOWN_SLOWKM 7.6⏱️45m

Quarterly LED aspect signal lamp replacement and relay contact resistance test.

Section: Byculla - Dadar Down Slow Line
Ticket: CR-SMMS-2026-0421β€’No heavy machine requiredβ€’+5m deadhead transit